Installation Filling Line & Pasteurizer – AB InBev Brewery Binh Duong

On August 2014, we were starting to install Bottle Filler, Conveyer & Pasteurizer for Guangdong Light Industrial Machinery Plant 2 Ltd (GLM2) – China at AB InBev Binh Duong Brewery (ABI)

This was the 1st brewery of AB InBev – the owner of Budweiser beer – Capacity 100 litter/year with owner capital of USD 45 millions. The brewery is located at VSIP – 2A, Tan Uyen District, Binh Duong Province.

Before, due to some reasons, we had refused installation jobs with Lehui – a main contractor for machineries, piping & tanks of ABI on May 2014, althrough we’d visited Lehui’s factories in Ningbo, Zhejiang, China.

Scope of supply of contract with GLM2 as follows:

  • Customs clearance, inland transportation & unloading equipment from HCMC ports to ABI – Tan Uyen, Binh Duong;
  • Installation: bottle filler, pasteurizer, bottle washer, conveyor, palletizer, depalletizer, conveyors, buffer tanks, cable trays & electrical works, other equipment & devices

Following are some pictures

AB InBev – Binh Duong Brewery

Office & Storage

Installing Bottle Filler

Installing Pasteurizer

Men in works